This guide follows French practice: French standards (NF DTU), French regulations and French bill conventions. Most sources are in French.
Take-off and the people who do it
- Métré (take-off)
- The calculation of the quantities of a piece of work from its dimensions. In the strict sense, French training frameworks keep the word for work actually carried out. The method is set out in how to do a take-off.
- Avant-métré (preliminary take-off)
- A take-off made from the drawings, before construction, to estimate a project or answer a tender.
- Métré d'exécution (as-built take-off)
- A take-off of the work actually carried out, measured on site or from updated drawings; it is used for valuations and the final account.
- Quantitatif (unpriced bill of quantities)
- The list of items with their quantities and units, without any prices.
- Estimatif (priced estimate)
- The bill of quantities with the prices added: each quantity multiplied by its unit rate, then totalled.
- Métreur (quantity surveyor, estimator)
- The technician who takes the dimensions, calculates the quantities and presents the take-off, in a cost consultancy, a design office or a contractor's office.
- Économiste de la construction (construction economist)
- A specialist in the cost of a project, involved from the brief to handover; the take-off is one of the foundations of the job.
- Attachement (measurement record)
- A written record, often with sketches, of the quantities carried out over a period or for part of the work.
- Situation de travaux (interim valuation)
- A periodic statement of the work carried out, used to pay the contractor during construction.
The contract documents
- DCE (tender documents)
- Dossier de consultation des entreprises: all the documents given to contractors so that they can price their tender.
- CCTP (particular technical specification)
- Cahier des clauses techniques particulières. It describes each item, what its price includes and, often, its method of measurement.
- CCAP (particular administrative conditions)
- Cahier des clauses administratives particulières: time limits, penalties, form of prices, documents with contractual value.
- Lot (trade package)
- The part of the works let to one contractor, often a single trade: structural work, drylining, painting…
- DPGF (breakdown of the lump-sum price)
- Décomposition du prix global et forfaitaire: the table that breaks a lump-sum price down item by item, close to a priced bill of quantities. The price does not follow the quantities, so those in the DPGF must be checked.
- Prix forfaitaire (lump-sum price)
- A price that pays for a set of works whatever the quantities actually carried out.
- Prix unitaire (unit rate)
- The price of one unit of work (one m², one ml, one item), applied to the quantities actually carried out.
- BPU (schedule of unit rates)
- Bordereau des prix unitaires: the contractual list of unit rates, each with its definition and unit.
- DQE (estimated bill of quantities)
- Détail quantitatif estimatif: the BPU rates multiplied by estimated quantities, to compare tenders. In principle, it is not contractual.
- Cadre de décomposition (breakdown form)
- The blank table (codes, descriptions, units) the contractor fills in; it sets the order and the breakdown of the take-off.
Units
- ml (mètre linéaire, linear metre)
- The unit of work measured by length: skirting, angle beads, pipe runs, kerbs. Writing “ml” distinguishes a quantity from a mere dimension in metres.
- m² (square metre)
- The unit of work measured by area: partitions, floor and wall finishes, render, roofing.
- m³ (cubic metre)
- The unit of work measured by volume: concrete, earthworks, backfill.
- u (unité, number)
- The unit of items counted one by one: doors, sanitary fittings, sockets, inspection chambers. British bills write “nr”.
- ens, ft (set, lump sum)
- Ensemble or forfait: an item paid as a single sum, such as the site set-up.
- kg, t
- The units of work measured by weight: reinforcement, structural steelwork.
- Unité d'ouvrage (unit of measurement)
- The unit in which an item is measured and paid. It is set by the form or the schedule of rates, never by habit.
Measuring on the drawing
- Échelle (scale)
- The ratio between the drawing and reality: at 1:50, 1 cm on the drawing is 50 cm. It should always be checked against a known dimension.
- Cote (dimension)
- A dimension written on the drawing. Where one exists, it is the reference for checking a measurement scaled from the drawing.
- Recherche de cote (working out a dimension)
- Calculating a dimension that is not written from other dimensions on the drawing; it is written into the calculations, like an assumption.
- Nu (face)
- The visible surface of a wall. Measurements are taken to the inside or outside face, structural or finished, according to the rule for the item.
- Axe (centre line)
- The middle line of a wall or partition. Measuring to the centre line or to the face is a convention to fix and to write down.
- Dans œuvre, hors œuvre (internal, external)
- A measurement taken inside the walls (dans œuvre) or outside them (hors œuvre).
- Développé (girth)
- The length of a shape laid flat: the perimeter of a room, the outline of a window reveal, the unfolded width of a flashing.
- Périmètre (perimeter)
- The length of the outline of an area. It gives the skirting, the edge angles or the waterproofing upstands.
- Hauteur sous plafond (floor-to-ceiling height)
- The clear height of a room, from finished floor to finished ceiling. It is not the height of a partition that goes up to the slab.
- Parties semblables (timesing)
- The number of times the same calculation repeats, written « 2f », « 3f » in front of the line: two identical flats, three windows of the same size.
- Coefficient de pente (pitch factor)
- The multiplier that converts an area or a length measured on plan to the true size of a roof slope.
- Surface de plancher (planning floor area)
- A French planning measure: the levels that are enclosed and covered, with a ceiling height above 1.80 m, measured to the inside face, after certain deductions. It is not a take-off quantity.
Deductions and openings
- Brut, net (gross, net)
- The quantity before and after deductions. Take-off calculations write both.
- Déduction (deduction)
- A part taken off a gross quantity: an opening in a wall, a void in a floor, a shower tray under floor tiling.
- Ouverture, baie (opening)
- A hole in a wall for a door or a window. It is deducted with its own height, not the height of the wall.
- Trémie (void)
- An opening in a floor or ceiling, for a staircase, a duct or a flue.
- Réservation (opening for services)
- A hole left in a piece of work for another trade (duct, pipe); depending on its size and the contract, it is deducted or not.
- Vide pour plein (voids not deducted)
- The rule that does not deduct openings smaller than a threshold, in m² per opening: the area counted in excess pays for the work around them. The threshold is the contract's and has no universal value (see the elevation take-off).
- Tableau, voussure, appui (reveal, soffit, sill)
- The returns around an opening: its sides, the underside of the lintel, its bottom edge. They are often counted separately, in ml.
Items and pieces of work
- Ouvrage élémentaire (elementary item)
- The smallest piece of work with its own price: same material, same thickness, same installation. The take-off is broken down to this level.
- Poste, article (item)
- A line of the form: a code, a description, a unit, a quantity.
- Désignation (description)
- The wording of an item, to be copied word for word into the take-off calculations.
- Localisation (location)
- Where what is counted lies: building, floor, flat, room, elevation.
- Mode de métré (method of measurement)
- The measurement rule for an item, written in the specification: « au m² réel mis en œuvre » (per m² actually installed), « joues comptées dans la surface » (sides included in the area)…
- Sujétions (incidental work)
- Constraints and small tasks included in the price without a line of their own: cutting, reinforcement, sealing (« tous détails et sujétions »).
- Plus-value, supplément (extra over)
- A price added to a base item for a variant, for example a moisture-resistant board as an extra over a standard partition.
- Sous-détail de prix (rate build-up)
- The breakdown of a unit rate into labour, materials and plant.
Writing it up
- Minute (calculation sheet)
- The sheet on which the take-off calculations are written, line by line; the British equivalent is the dimension sheet.
- Note de métré (take-off calculations)
- The document that justifies each quantity: location, dimensions, calculation, deductions, total. See take-off calculations.
- Report (carried forward)
- The total of a page carried to the top of the next one.
- Récapitulatif (summary)
- The table of totals per item, without the detail of the calculations.
- Plan de repérage (location drawing)
- A drawing on which each item counted is marked, in colour or with a reference, so that its line in the calculations can be found.
- Arrondi (rounding)
- Each quantity is written with a fixed number of decimal places; a total that can be checked is the sum of the values written.
One line of take-off calculations, word by word
Here is a line of French take-off calculations, then how to read it with the words above.
6.3 Plinthes bois — R+1, chambres 2 et 3 — 2f × [2 × (3,40 + 3,10) − 0,80] = 2f × 12,20 = 24,40 ml
| Element | What it is |
|---|---|
| 6.3 | The code of the item in the breakdown form |
| Plinthes bois | The description (timber skirting), copied from the form |
| R+1, chambres 2 et 3 | The location: first floor, bedrooms 2 and 3 |
| 2f | Timesing: the two bedrooms have the same dimensions |
| 2 × (3,40 + 3,10) = 13,00 | The girth of the room, here its perimeter to the inside face |
| − 0,80 | The deduction for the door opening, where there is no skirting |
| 12,20 | The net quantity for one bedroom |
| 24,40 ml | The quantity of the item, in linear metres |
The same words in Kotelys
Kotelys uses this vocabulary in English; a few words have a precise meaning there.
- Type
- One item of the take-off: a name, a colour on the drawing, a total. All the objects of a type add up.
- Length, Area, Count
- The three measuring tools, which give ml, m² and u.
- Height, thickness
- Settings of a type: a length with a height gives a wall area, an area with a thickness gives a volume.
- Deduction
- A void drawn inside an area and taken off it.
- Opening
- A door or window placed on a length, with its own height; only its area is taken off the wall.
- Layer
- A way of sorting the objects of a drawing, which can be shown, hidden or locked.
- Zone
- Part of a drawing (flat, floor, phase); the “Break down by zone” box of the reports gives the quantities location by location.
These words describe what you draw: Kotelys does not read the specification and does not choose the method of measurement for you.

Further reading: Kotelys features, and the other guides.
Sources
- Éduscol, Bac Pro Technicien d'études du bâtiment framework: preliminary take-off and take-off, elementary items, calculation sheets, measurement records, rate build-up
- Éduscol STI, BTS Management économique de la construction framework (Official Journal, 31/01/2021): units of measurement, location drawings
- Éduscol STI, BTS Études et économie de la construction, 2019 session, paper U41, marking scheme: timesing, working out dimensions, carried-forward totals
- Éduscol STI, CAP MPI 2021 technical file: specification with method of measurement, extras and incidental work
- French National Assembly, written question no. 41217 and the ministry's answer (preliminary take-off, DPGF)
- code-commande-publique.com, « Décomposition du prix forfaitaire (DPGF) »: lump-sum prices and quantities
- code-commande-publique.com, « Bordereau des prix unitaires (BPU) »
- code-commande-publique.com, « Détail quantitatif estimatif (DQE) »
- Service-public.fr, « Surface de plancher, emprise au sol et surface taxable d'une construction »
- UNTEC, « Devenir économiste de la construction »
Thresholds and values described as “taken for the example” are not rules: those of your contract (specification, bill of quantities) always prevail.